IT/NTS Reorganization Implementation Milestones ver. 3a - 2/2/2007
Area Group Implementation Milestones   Feb March April May June

Admin Services
IT Fiscal Services Staff hire begins     complete
Org Strat. & Staff Dev Staff moves and reporting changes Phase 1 Phase 2

Information Analysis
& Design 
Info Analysis & Design  Discussions / planning begins   complete
Info Analysis & Design  Staff & reporting moves  begins /
complete

Information Security 
Compliance  Staff moves & reporting changes / Implementation begins /
complete
Security Mgmt / Daily Operations Staff moves & reporting changes / Implementation begins /
complete




Physical
Infrastructure
Enterprise Network Planning & Support Staff moves & reporting changes  begins /
complete
Infrastructure & Data Center Support Implementation  begins /
complete
Infrastructure & Data Center Support Staff moves & reporting changes   Phase 1 Phase 2










Service Management
& Assessment
CRSD: Customer Service Center Call center discussions begins     complete
CRSD: Customer Service Center Staff hires, moves & reporting changes begins       complete
CRSD: Customer Service Center Implementation of new front-line services begins /
complete
CRSD: Desktop Support Staff moves & reporting changes / Implementation begins /
complete
Network Ops Center Implementation  begins       complete
Process & Planning Mgmt Staff moves & reporting changes Phase 1 Phase 2
Project Mgmt Project management support replacement - search begins complete
Project Mgmt Implementation begins complete
Research & Consulting Serv. Staff moves & reporting changes begin       complete
Research & Consulting Serv. Implementation  begins complete
RCS: Constituency Support  Staff moves & reporting changes begins /
complete
User Documentation & Web Content Staff moves & reporting changes / Implementation begins /
complete










System Design
and Delivery
All Sys. Design & Del. Units Staff and project discussions begins
All Sys. Design & Del. Units Implementation  begins   complete
Enterprise System Dev. Implementation begins   complete
Enterprise Sys. Integration Staff moves & reporting changes - managers begins       complete
Enterprise Sys. Integration Implementation begins       complete
ESI: IT System Development  Staff moves & reporting changes begins complete
ESI: IT System Development  Implementation begins   complete
ESI: System Integration Staff moves & reporting changes / Implementation begins       complete
ESI: Web Development / Interface Design Staff moves & reporting changes begins /
complete
Software QA/Testing Discussions/planning begins     complete
Software QA/Testing Staff moves & reporting changes begins /
complete


Technology Platforms
Application Administration Staff moves & reporting changes begins complete
Application Administration Voyager support replacement - search process  begins     complete
System Administration Staff moves & reporting changes begins /
complete