| IT/NTS Reorganization Implementation Milestones | ver. 3a - 2/2/2007 | ||||||||||
| Area | Group | Implementation Milestones | Feb | March | April | May | June | ||||
Admin Services |
IT Fiscal Services | Staff hire | begins | complete | |||||||
| Org Strat. & Staff Dev | Staff moves and reporting changes | Phase 1 | Phase 2 | ||||||||
Information Analysis & Design |
Info Analysis & Design | Discussions / planning | begins | complete | |||||||
| Info Analysis & Design | Staff & reporting moves | begins / complete |
|||||||||
Information Security |
Compliance | Staff moves & reporting changes / Implementation | begins / complete |
||||||||
| Security Mgmt / Daily Operations | Staff moves & reporting changes / Implementation | begins / complete |
|||||||||
Physical Infrastructure |
Enterprise Network Planning & Support | Staff moves & reporting changes | begins / complete |
||||||||
| Infrastructure & Data Center Support | Implementation | begins / complete |
|||||||||
| Infrastructure & Data Center Support | Staff moves & reporting changes | Phase 1 | Phase 2 | ||||||||
Service Management & Assessment |
CRSD: Customer Service Center | Call center discussions | begins | complete | |||||||
| CRSD: Customer Service Center | Staff hires, moves & reporting changes | begins | complete | ||||||||
| CRSD: Customer Service Center | Implementation of new front-line services | begins / complete |
|||||||||
| CRSD: Desktop Support | Staff moves & reporting changes / Implementation | begins / complete |
|||||||||
| Network Ops Center | Implementation | begins | complete | ||||||||
| Process & Planning Mgmt | Staff moves & reporting changes | Phase 1 | Phase 2 | ||||||||
| Project Mgmt | Project management support replacement - search | begins | complete | ||||||||
| Project Mgmt | Implementation | begins | complete | ||||||||
| Research & Consulting Serv. | Staff moves & reporting changes | begin | complete | ||||||||
| Research & Consulting Serv. | Implementation | begins | complete | ||||||||
| RCS: Constituency Support | Staff moves & reporting changes | begins / complete |
|||||||||
| User Documentation & Web Content | Staff moves & reporting changes / Implementation | begins / complete |
|||||||||
System Design and Delivery |
All Sys. Design & Del. Units | Staff and project discussions | begins | ||||||||
| All Sys. Design & Del. Units | Implementation | begins | complete | ||||||||
| Enterprise System Dev. | Implementation | begins | complete | ||||||||
| Enterprise Sys. Integration | Staff moves & reporting changes - managers | begins | complete | ||||||||
| Enterprise Sys. Integration | Implementation | begins | complete | ||||||||
| ESI: IT System Development | Staff moves & reporting changes | begins | complete | ||||||||
| ESI: IT System Development | Implementation | begins | complete | ||||||||
| ESI: System Integration | Staff moves & reporting changes / Implementation | begins | complete | ||||||||
| ESI: Web Development / Interface Design | Staff moves & reporting changes | begins / complete |
|||||||||
| Software QA/Testing | Discussions/planning | begins | complete | ||||||||
| Software QA/Testing | Staff moves & reporting changes | begins / complete |
|||||||||
Technology Platforms |
Application Administration | Staff moves & reporting changes | begins | complete | |||||||
| Application Administration | Voyager support replacement - search process | begins | complete | ||||||||